Tullholmsviken

Location: Karlstad

Customer: Consto AB

Assembly start: 2022-10-03

Assembly completed: 2024-05-16

Size: 135 tons of steel, 26 000 m2 of concrete walls, 4000 m2 of slab

Tullholmsviken

Karlstad is growing and in collaboration with Consto AB we have since 2020 contributed to creating over 900 apartments. 

The project includes the full responsibility for assembly and delivery of steel, concrete walls, and floors for blocks 3, 4, and 7 in Tullholmsviken. These blocks will include residential buildings, commercial spaces, parking garages, and pleasant outdoor environments for residents and visitors. The development of Karlstad’s city center is an initiative by Magnolia Bostad AB, and the project is being carried out in collaboration with Consto AB. Assembly is scheduled to be completed by spring 2024.